rivermobster
Club Banned
- Joined
- Dec 28, 2009
- Messages
- 60,060
- Reaction score
- 61,195
So bad azz...
Deck rack or tunnel?Been busy drawing up
Specifications for bakery ovens.
We used a revolving oven at Snyders in the 70’s. Hand twisted.…….Deck rack or tunnel?
Any update pics???We used a revolving oven at Snyders in the 70’s. Hand twisted.…….
Your'e a good sport, Funny too!We used a revolving oven at Snyders in the 70’s. Hand twisted.…….
Oh ! That brief discussion and smidgen of insight was for this little clapboard man-shed ?I have to give credit to Taboma. He helped with the electric.
Oh ! That brief discussion and smidgen of insight was for this little clapboard man-shed ?
Had I realized that, I'd have pulled out the old mil-specs and shop drawings for the LCAC (Landing Craft Air Cushion) apron shore power vaults, instead of the Harbor Freight Electrical Catalog
I am however just slightly intrigued why such a large garage door opening. Apparently wide enough to accommodate something much wider than a rotary wing aircraft, like a corporate Jet as one example, when I've yet to see anything resembling a runway or airport nearby ??
Love the building and certainly enjoying following along, thanks for sharing, very cool indeed sir.
I can’t stop laughing about the word “clapboard”. You might be older than me.Oh ! That brief discussion and smidgen of insight was for this little clapboard man-shed ?
Had I realized that, I'd have pulled out the old mil-specs and shop drawings for the LCAC (Landing Craft Air Cushion) apron shore power vaults, instead of the Harbor Freight Electrical Catalog
I am however just slightly intrigued why such a large garage door opening. Apparently wide enough to accommodate something much wider than a rotary wing aircraft, like a corporate Jet as one example, when I've yet to see anything resembling a runway or airport nearby ??
Love the building and certainly enjoying following along, thanks for sharing, very cool indeed sir.
Hoping for August but might not make it.Nice progress, now I understand the vertical openings- stairwell, dig the bike rack, proximity to the airport would have been a giveaway, nice play keeping that close to the vest! Carry on. Expected completion date?
Yeah, lead times can be brutal, we had a "forward planning dept" that dealt soley in that to try and prevent the "surprises" they still happen.Hoping for August but might not make it.
The 385 yard pour for the floor got pushed out a week for lack of that large of a batch unless we wanted to break it up which we didn’t as it is polished. We have another 15,000 feet of 10 inch to pour outside after that, which is tough to get.
Although everything has been ordered long ago, some items are slipping on timing. For example the SES is a year lead time, the UST for storm water is supposed to be here July 15 and was 6 months. Everything has a super long lead time and everyone is super swamped. So I’m now hoping for September?
Unfortunately no, but I will be able to whip up some doughnuts if you stop by.So it's not going to be a industrial Pretzel Factory?
Did you find the spot in the corner where I carved my initials Wednesday evening?
LOL. You need a better pump truck.Did you find the spot in the corner where I carved my initials Wednesday evening?
I guess I missed what was happening with the exterior walls I haven’t been keeping up. Hopefully nothing too serious.LOL.
No, which corner? I did carve mine.
Are you going to fix my exterior walls?
Just a few business aviation assets that get bought/sold/reconfigured over the course of a year. Primarily rotorcraft from LE.Can we find out what’s going in it yet?
The fire sprinkler guy better get his pipe in the air or they are going to get buried. Looks like the steel studs have been delivered.
Just a few business aviation assets that get bought/sold/reconfigured over the course of a year. Primarily rotorcraft from LE.
They come and they go.
We are still trying to work through using tyco window sprinklers as an alternative to fire glazing. Fire glazing is a year backlogged despite the alleged oncoming economic depression.The fire sprinkler guy better get his pipe in the air or they are going to get buried. Looks like the steel studs have been delivered.
MD products have become ridiculously expensive with the bankruptcy of MD. Although we have a ton of spares and own several now, Airbus has strangely become a more economical option for operators. Who would have ever thought Airbus would be more economical?Soooo maybe something MD, possibly a 520N, or a 500E?
As a non owner but obsessive enthusiast, I would never have thought that second part. If we’re talking Leo and airbus, definitely has to be AS350 or like models.MD products have become ridiculously expensive with the bankruptcy of MD. Although we have a ton of spares and own several now, Airbus has strangely become a more economical option for operators. Who would have ever thought Airbus would be more economical?
First thing I notice is the lap on all the rebar is along the same line. Call it a gridline for instance. How does that hold up structurally? I was taught to offset the laps from each other as its a weak point when they are all placed in line with each other.
A good E model is 1.5 now. A good F is over 2.As a non owner but obsessive enthusiast, I would never have thought that second part. If we’re talking Leo and airbus, definitely has to be AS350 or like models.
I just pay the bills. I’mFirst thing I notice is the lap on all the rebar is along the same line. Call it a gridline for instance. How does that hold up structurally? I was taught to offset the laps from each other as its a weak point when they are all placed in line with each other.
Usually the architect needs to get the window sprinklers approved. I have in the past used a water curtain / deluge system to flood the glass with Water. Install the heads 6’ on center on both sides of the glass. The Tyco heads are expensive.We are still trying to work through using tyco window sprinklers as an alternative to fire glazing. Fire glazing is a year backlogged despite the alleged oncoming economic depression.
If you have any special documentation or tricks of the trade on how to get that alternative accepted through the process I am all ears.
MD products have become ridiculously expensive with the bankruptcy of MD. Although we have a ton of spares and own several now, Airbus has strangely become a more economical option for operators. Who would have ever thought Airbus would be more economical?
You should post more about work…..I’d read it ha!A good E model is 1.5 now. A good F is over 2.
A good B2 is a million and a good B3 is 1.3. A B3E is expensive. Both a B2 and a B3 will outperform a D, E or F all day long and are now cheaper to run.
MD’s are slowly becoming rich guys toys, not work assets.
There are still some high time machines out there working reasonably, but we are talking 10 to 20 thousand hour stuff.
It’s hard to make a 500 pencil anymore given an R44 can do 75% of the jobs a 500 used to.
Have you priced or tried to source fire glazing since 2019?Usually the architect needs to get the window sprinklers approved. I have in the past used a water curtain / deluge system to flood the glass with Water. Install the heads 6’ on center on both sides of the glass. The Tyco heads are expensive.
Two hour rated 20 linear feet by 10 feet tall glass walls on both first and second story of office to hangar.Small kitchen window on one of my multi-family projects was $3,700 for 45min rated.
Lol!!We used a revolving oven at Snyders in the 70’s. Hand twisted.…….
I see walls but no MEP trades at the deck level. I'm sure they coordinated with the new steel studs.Progress is always a good thing, glad to see it moving forward
They are all there at the same time both upstairs and downstairs. You can see electrical boxes in the walls and in the floors upstairs. The two guys in picture 2 are the plumbers, and the sprinkler guy is like get that shit done before I show up as I don't want anyone screwing up my stuff. All his pipe is on a giant wood pallet on the lot.I see walls but no MEP trades at the deck level. I'm sure they coordinated with the new steel studs.
I have a project where the GC is doing the same thing with the studs. Giving us 2 days to rough in our pipes.
We engineer and pre-fab / weld all our pipes in our shop before we send it to the jobsite. If it fits without having to pull out our pipe machine for too many changes due to other trades its a good thing. Some companies prefer to cut in the field.They are all there at the same time both upstairs and downstairs. You can see electrical boxes in the walls and in the floors upstairs. The two guys in picture 2 are the plumbers, and the sprinkler guy is like get that shit done before I show up as I don't want anyone screwing up my stuff. All his pipe is on a giant wood pallet on the lot.
I just pay the bills. Let's see how it goes.
Did you resolve the issues with the glass wall?