Cobalt232
Well-Known Member
- Joined
- Dec 26, 2018
- Messages
- 1,320
- Reaction score
- 1,737
Hey...
For the past few months we have been doing a TI in the next unit over for new lab space. A couple of weeks ago, we started installing a piece of equipment that I thought required 208v electrical service that we have coming into the building (3-120 legs). It is a piece of equipment from the mid 90's that is used to process film made in Denmark. We have another one of them running next door on 208v (120x3 legs) for the previous 20 or so years with no issues. I pulled this new to us piece of equipment out of a lab in Denver 3 years ago and it has been in storage since.
I'm using an installer that has maintained our equipment for the past 15 or so years. He originally worked for Kodak, where he installed these machines since the 80's. He is the last one of these guys around as all the others have died, and he is in bad shape too. When he showed up to assemble the equipment a couple of weeks ago, he said the electrical service needed to be 3 phase with one leg 208 and the 2 others at 120. I thought he was confused. When the electrician who did the TI showed up he had never heard of this electrical service and said he just built it to the plans. When the architect and his engineer came in early in the project, I showed them the similar existing piece of equipment and told them the other machine will have similar electrical requirements based on them being similar machines from the same company.
We fired up the equipment last week and the single-phase things work (pumps, etc.) but the 3 phase motor isn't getting any power to run. The installer blames it on the electrical service and said other labs have had this same issue. So I called the electrician and he said he would call another electrician friend for some info. Unfortunately, his friend is on vacation until the 15th and I only have the installer available until the 10th (next chemo round).
So, I did a bunch of Googling and learned a bit about 'High-leg', 'Wild-leg', Stinger-leg' service that we apparently need but don't have. Do we need a transformer? I don't wan't to fry my equipment as replacements are non-existent.
What type of contractor do I need to help with this?
.
For the past few months we have been doing a TI in the next unit over for new lab space. A couple of weeks ago, we started installing a piece of equipment that I thought required 208v electrical service that we have coming into the building (3-120 legs). It is a piece of equipment from the mid 90's that is used to process film made in Denmark. We have another one of them running next door on 208v (120x3 legs) for the previous 20 or so years with no issues. I pulled this new to us piece of equipment out of a lab in Denver 3 years ago and it has been in storage since.
I'm using an installer that has maintained our equipment for the past 15 or so years. He originally worked for Kodak, where he installed these machines since the 80's. He is the last one of these guys around as all the others have died, and he is in bad shape too. When he showed up to assemble the equipment a couple of weeks ago, he said the electrical service needed to be 3 phase with one leg 208 and the 2 others at 120. I thought he was confused. When the electrician who did the TI showed up he had never heard of this electrical service and said he just built it to the plans. When the architect and his engineer came in early in the project, I showed them the similar existing piece of equipment and told them the other machine will have similar electrical requirements based on them being similar machines from the same company.
We fired up the equipment last week and the single-phase things work (pumps, etc.) but the 3 phase motor isn't getting any power to run. The installer blames it on the electrical service and said other labs have had this same issue. So I called the electrician and he said he would call another electrician friend for some info. Unfortunately, his friend is on vacation until the 15th and I only have the installer available until the 10th (next chemo round).
So, I did a bunch of Googling and learned a bit about 'High-leg', 'Wild-leg', Stinger-leg' service that we apparently need but don't have. Do we need a transformer? I don't wan't to fry my equipment as replacements are non-existent.
What type of contractor do I need to help with this?